April 2016 - Window and Patios

We got a lot of stuff started this month, just not much finished! The windows were delivered; I ended up using the Integrity line of Marvin windows. The commercial grade aluminum units I was planning on using didn't work out. The Integrity units are really nice, and the added bonus is that they have a 7-10 day lead time! We also started the Enduramax masonry veneer system from Oldcastle/ Adams Products. The system is designed as a fulled anchored masonry veneer over a layer of continuous insulation with built in drainage channels. We had to install the first course of the system in order to pour the concrete patios around the house; and we had to pour the patios before installing the majority of the Integrity Sliding Doors.

Windows and Door at the Gallery, overlooking the big rock.

Patio slab prep. Also, the beginnings of the install of the Enduramax masonry veneer system.


More patio slab prep - there are nine of these patio areas.

Living room patio slabs poured.

Misha on the Bobcat again!

No comments:

Post a Comment